Q351: What is a characteristic of the waterfall model?
  • A: Non-linear approach to development
  • B: Multiple iterations per phase
  • C: Linear progression through phases
  • D: Complex interaction with users
View Answer
C

Q352: What should be prioritized in designing a database?
  • A: User interface
  • B: Scope and structure of the database
  • C: Documentation requirements
  • D: Availability of resources
View Answer
B

Q353: What does a logical design phase involve?
  • A: Finalizing user manuals
  • B: Converting design specifications into executable programs
  • C: Breaking down the logical design into units
  • D: Testing user interfaces
View Answer
C

Q354: What is the main focus of the incremental model in software development?
  • A: Iteration of the product
  • B: Development and maintenance
  • C: Redesign of the product
  • D: Cost reduction
View Answer
B

Q355: In the incremental model, what is the purpose of the first increment?
  • A: To provide advanced functions
  • B: To address basic requirements
  • C: To finalize the product
  • D: To gather user feedback
View Answer
B

Q356: Which of the following is NOT a characteristic of the incremental model?
  • A: Partial systems built successively
  • B: Highest priority requirements tackled early on
  • C: All requirements are flexible
  • D: Requirements for an increment are frozen
View Answer
C

Q357: The incremental model combines elements of which two models?
  • A: Agile and Waterfall
  • B: Waterfall and Prototyping
  • C: Prototyping and Iterative
  • D: Agile and Iterative
View Answer
B

Q358: What is one of the benefits of using the incremental model?
  • A: Higher costs for clients
  • B: Immediate feedback from the client
  • C: Difficult to manage requirements
  • D: Larger system perspective unavailable
View Answer
B

Q359: Fill in the blank: In the iterative model, the ________ step creates a base version of the system.
  • A: Implementation
  • B: Initialization
  • C: Analysis
  • D: Design
View Answer
B

Q360: What is the primary risk associated with iterative models?
  • A: Overestimating costs
  • B: Scope creep
  • C: Delays in implementation
  • D: Poor user feedback
View Answer
B